Fixed-Price Construction Contracts in North Carolina: Understanding the Risks Before You Sign
By Caitlin S. Truelove
Attorney at Law

Fixed-price construction contracts remain one of the most common project delivery methods in North Carolina. Owners often prefer the certainty of a predetermined contract sum, while contractors may view fixed-price agreements as an opportunity to maximize profitability through efficient project management.
However, a fixed-price contract also places significant financial risk on the contractor. Unexpected labor shortages, material price increases, design issues, weather delays, and scope disputes can quickly transform a profitable project into a costly one.
Before entering into a fixed-price agreement, North Carolina contractors should understand how these contracts allocate risk and what contractual protections can help preserve profitability.
What Is a Fixed-Price Construction Contract?
A fixed-price contract—sometimes referred to as a lump-sum contract—is an agreement under which the contractor agrees to complete a defined scope of work for a specified contract price.
Unlike cost-plus contracts, where the owner bears much of the risk of cost overruns, fixed-price contracts generally shift that risk to the contractor.
If the contractor's actual costs exceed the contract price, the contractor typically absorbs the loss unless the contract permits additional compensation through change orders or other contractual remedies.
Project owners and general contractors are often attracted to fixed-price contracts because they provide: budget certainty; simplified financing and project planning; reduced administrative oversight of construction costs; and greater predictability regarding total project expenditures.
For public and private owners alike, a fixed-price arrangement can make project costs easier to manage and forecast.
The Risks Contractors Face
While a fixed-price contract can be profitable when a project proceeds as anticipated, construction contracts are often drafted by the general contractor, and thus heavily in favor of the general contractor when something goes wrong on the project. You as the subcontractor need to vigorously negotiate for favorable terms, and you must carefully evaluate several significant risks.
Material Price Escalation
Over the past several years, North Carolina contractors have experienced substantial fluctuations in the cost of materials. Terms of material price escalation and who would bear the cost of such increases have become more important than ever. We have seen these terms many times in contracts, and it has always been that the contractor bears the risk and responsibility for paying these costs. When material costs make up the majority of your bid, contractual protections against material price escalations are incredibly important. While your construction bid may allow you to absorb some material cost increases, given recent market volatility, you should negotiate for a provision that allows adjustment for significant increases in material costs.
Design Errors and Omissions
Owners and general contractors expect subcontractors to deliver projects according to plans and specifications prepared by architects and engineers. However, incomplete or defective design documents can create costly delays and disputes. We have seen many construction contracts, wherein the subcontractor agreed to bear financial responsibility for design errors and omissions caused by the architect and engineer. While the validity of such clauses could be argued in court, it is best practice to review any construction contract for such clauses and have them removed before signing the contract.
Unforeseen Site Conditions
Subsurface conditions, environmental issues, hidden utilities, and unsuitable soils can substantially increase construction costs. A contractor that fails to investigate site conditions adequately before bidding may encounter significant financial exposure. Additionally, most fixed-price construction contracts will state that you are required to inspect the site before you begin work, and notify the general contractor within so many days if other subcontractors have caused issues with the project site, or you may bear some financial responsibility for failing to notify the general contractor of the issues.
Delays Beyond the Contractor's Control
Weather events, permitting issues, utility delays, supply chain disruptions, and owner-caused delays can affect project performance. You should make sure that a change order for additional days may be issued to address weather delays. You should ensure that the contract provides appropriate extensions of time and, where possible, compensation for owner-caused delays as well.
You will also want to make sure that the force majeure provision, which should address extraordinary events such as natural disasters, supply chain interruptions, labor disruptions, and governmental actions that affect project performance, allows for you to submit a change order for additional time and costs to address any delays and increased material costs due to subsequent supply chain issues.
Change Orders: The Contractor's Lifeline
One of the most important protections in a fixed-price contract is a well-defined change-order process. Scope changes frequently occur during construction. Additional work performed without a signed change order make up a large portion of the payment disputes our office has dealt with. Make sure that you understand, how, why, and when you are allowed to request a change order on the project before signing the contract. We have seen contracts where the general contractor reserved the right to order the subcontractor to perform the work without a signed change order when the parties could not agree on the cost of the change order. Failure to comply with contractual procedures may jeopardize your ability to recover additional compensation, so it is critically important to negotiate for firm, clear terms and conditions for change orders and work outside of the scope of the contract.
Termination
Often times, a fixed-price construction contract will allow the general contractor to terminate the contract for a number of reasons, even allowing the general contractor to terminate the contract for convenience. You will want to carefully review and negotiate any termination provisions with the general contractor and vigorously negotiate to allow you to terminate the contract as well for reasons such as non-payment.
Conclusion
Fixed-price contracts can offer significant opportunities for North Carolina contractors, but they also transfer substantial risk to the party performing the work. Material price volatility, unforeseen site conditions, and scope changes can quickly erode anticipated profits.
By carefully evaluating contract terms, documenting project changes, and understanding how risk is allocated before signing, contractors can better protect their businesses and improve the likelihood of a successful project outcome.
The most effective risk management strategy begins long before construction starts—with a thorough review and negotiate for favorable terms in the contract itself.
Wisdom, Experience, Results
Learn More from Vann Attorneys
Vann Attorneys stands ready to meet the diverse needs of clients ranging from individuals to privately held family businesses to corporations with national distribution. The firm represents clients throughout North Carolina and the United States. We periodically publish content that is relavant to our clients and community. Keep reading our 'News & Events' page on the topics most important to you and your business.
Proven
Experience on
Your Side
Leave a message
Raleigh Office
RALEIGH HOURS
| Mon | 8am - 5pm |
|---|---|
| Tues | 8am - 5pm |
| Wed | 8am - 5pm |
| Thurs | 8am - 5pm |
| Fri | 8am - 5pm |
Charlotte Office
CHARLOTTE HOURS
| Mon | 8am - 5pm |
|---|---|
| Tues | 8am - 5pm |
| Wed | 8am - 5pm |
| Thurs | 8am - 5pm |
| Fri | 8am - 5pm |